 Post subject: Re: Our kitchen/bath project
PostPosted: Thu Jul 31, 2008 9:19 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Thursday, they put in the window sills and the glass transom above the door. We put on the backsplash tiles that go over the range. They're a copper faced ceramic tile. We also started installing the laminate "floating" floor.

Don't let anyone fool you into thinking this kind of floor is easy to install. It's very tricky, and the devil is in the details. It takes a lot of thinking and planning ahead. Also, the veneer is rather fragile until it's installed, and one missed hammer blow will cause significant damage.


Attachments:
P1020137 (Medium).JPG
P1020137 (Medium).JPG [ 37.98 KB | Viewed 552 times ]
P1020136 (Medium).JPG
P1020136 (Medium).JPG [ 33.82 KB | Viewed 548 times ]
P1020135 (Medium).JPG
P1020135 (Medium).JPG [ 79.46 KB | Viewed 549 times ]
Top
 Profile  
 
 Post subject: Re: Our kitchen/bath project
PostPosted: Fri Aug 01, 2008 5:00 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Friday, we finished the kitchen and pantry floors, and the drywall finishers came in and finished up their work in the bathroom.


Attachments:
P1020141 (Medium).JPG
P1020141 (Medium).JPG [ 52.15 KB | Viewed 545 times ]
Top
 Profile  
 
 Post subject: Re: Our kitchen/bath project
PostPosted: Mon Aug 04, 2008 4:30 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Monday, the bathroom tile was installed, except the tile that needs milling. They also installed the pantry shelves, and made a nice step nosing for the pantry. The shower floor is tumbled marble 2"x2" tiles, and the rest is travertine 18"x18" tiles.


Attachments:
P1020195 (Medium).JPG
P1020195 (Medium).JPG [ 73 KB | Viewed 539 times ]
P1020193 (Medium).JPG
P1020193 (Medium).JPG [ 62.51 KB | Viewed 540 times ]
P1020192 (Medium).JPG
P1020192 (Medium).JPG [ 57.82 KB | Viewed 539 times ]
P1020191 (Medium).JPG
P1020191 (Medium).JPG [ 30.87 KB | Viewed 537 times ]
Top
 Profile  
 
 Post subject: Re: Our kitchen/bath project
PostPosted: Wed Aug 06, 2008 3:16 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Tuesday, they finished the bathroom tile work, and are scheduled to return Friday to grout it. We started painting the pantry, too.

The strip of small mosaic stone tiles provides a transition to the white ceramic tile, which is at a slightly different height than the travertine floor tile.


Attachments:
P1020216 (Medium).JPG
P1020216 (Medium).JPG [ 54.47 KB | Viewed 529 times ]
P1020215 (Medium).JPG
P1020215 (Medium).JPG [ 37.76 KB | Viewed 530 times ]
Top
 Profile  
 
 Post subject: Re: Our kitchen/bath project
PostPosted: Sun Aug 10, 2008 10:02 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Thursday, they grouted and finished up the tile work. Friday they painted some, and did some trim work. Then Saturday we painted the bathroom walls and ceiling, installed the shower head, and took a shower. The shower curtain is temporary until we get a glass one.


Top
 Profile  
 
 Post subject: Re: Our kitchen/bath project
PostPosted: Thu Aug 14, 2008 5:54 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Just a little cleanup by us on Monday, then Tuesday the wall painting was finished. Wednesday was minor tasks like adding tile to the sloped transition from the house to the kitchen, then Thursday they installed the countertops and the gas service. Two gas cylinders, one so when we run out we can switch over and call for a refill at our leisure.

The dining table is temporary until we get a good one.


Attachments:
P1020240 (Medium).JPG
P1020240 (Medium).JPG [ 30.85 KB | Viewed 507 times ]
P1020239 (Medium).JPG
P1020239 (Medium).JPG [ 55.94 KB | Viewed 511 times ]
P1020238 (Medium).JPG
P1020238 (Medium).JPG [ 58.84 KB | Viewed 509 times ]
P1020237 (Medium).JPG
P1020237 (Medium).JPG [ 102.33 KB | Viewed 510 times ]
Top
 Profile  
 
 Post subject: Re: Our kitchen/bath project
PostPosted: Sat Aug 16, 2008 1:13 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Friday's big push almost got it all done. Just a few items left that we hope to get done ourselves ASAP. The undercounter lights are in, the bathroom sink is in, and quarter-round molding in the kitchen is in. Still waiting for missing parts for the range hood, and we've been struggling with installing the toilet. We went through three wax rings before realizing we need the thick ones.


Attachments:
P1020256 (Medium).JPG
P1020256 (Medium).JPG [ 27.33 KB | Viewed 506 times ]
P1020255 (Medium).JPG
P1020255 (Medium).JPG [ 40.23 KB | Viewed 508 times ]
Top
 Profile  
 
 Post subject: Re: Our kitchen/bath project
PostPosted: Sun Aug 17, 2008 2:17 pm 
Offline
Site Admin

Joined: Sun Dec 30, 2007 9:34 am
Posts: 63
Over the weekend, we did a few minor touch up things, and I installed the kitchen sink drain line. Still left are painting the doors and frames, and other minor touch ups.


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 28 posts ]  Go to page Previous  1, 2, 3

All times are UTC - 5 hours


Who is online

Users browsing this forum: No registered users and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB © 2000, 2002, 2005, 2007 phpBB Group
All drawings © 2008 John Reep, Architect